Major Utilities Projects
SPENCER CREEK TRUNK SEWER REPLACEMENT PROJECT
Project Cost: $910,861.65
Contractor: Lamke Trenching & Excavating, Inc.
Scope: This project is replacing old sanitary sewer pipes with more than 4,500 lineal feet of sewer line at the back of City Centre Park, behind ball fields and St. Peters Rec-Plex South. Much of the work is being done through a trenchless process called "pipe bursting." New, larger piping is being placed inside the old pipe. The old pipe bursts into pieces and the new pipe will remain in its place. Through this method, there will be less disruption to the park and its facilities. The work consists of: pipe bursting 3,082 lineal feet of 24-inch fiberglass sanitary sewer line with 26-inch high-density polyethylene (HDPE) piping; pipe bursting 964 lineal feet of 18-inch fiberglass sanitary sewer with 20-inch HDPE piping; and the construction of 487 lineal feet of 24-inch reinforced concrete pipe and 16 lineal feet of 8-inch PVC gravity sanitary sewer.
Currently: The contractor is working on pipe bursting the 24-inch fiberglass line.
Aldermanic Ward: 1
BACK TO THE TOP
I-70 RELIEVER SANITARY SEWER PROJECT – COMPLETED
Project Cost: $181,308
Contractor: S&S Utilities Inc.
Completed in 2011: This project constructed a new gravity sewer from Arrowhead Industrial Drive to Highway C to accommodate the construction of the new Salt River Road (I-70 Reliever) Project.
Aldermanic Wards: 1 and 3
BACK TO THE TOP
EMERALD COVE LIFT STATION & FORCE MAIN – COMPLETED
Project Cost: $412,000
Contractor: Pipeworks Inc.
Completed in 2011: This project constructed a new sanitary lift station and force main to serve the Emerald Cove District Sewer Area. This area consists of 35 acres bounded by Belleau Creek Road, Veterans Memorial Parkway and the Estates of Chateau Woods subdivision.
Aldermanic Ward: 1
BACK TO THE TOP
SALT RIVER ROAD SANITARY PUMP STATION – COMPLETED
Project Cost: $332,000
Contractor: S&S Utilities Inc.
Completed in 2011: This project constructed a new sanitary pump station to serve the Old
Town Industrial Development Area north of Ecology Drive.
Aldermanic Ward: 1
BACK TO THE TOP
SALT RIVER ROAD GRAVITY SEWER PROJECT - COMPLETED
Project Cost: $300,000
Contractor: S&S Utilities, Inc.
Completed in 2010: This project installed about 4,200 lineal feet of new sanitary sewer
along the recently constructed Salt River Road extension north of
Ecology Drive. This sewer will connect to a new sanitary sewer pump
station being constructed under a separate contract.
Aldermanic Ward: 1
BACK TO THE TOP
AERATED STATIC PILE COMPOST FACILITY - COMPLETED
Project Cost: $1,610,000
Contractor: Engineered Compost Systems & Kozeny-Wagner, Inc.
Completed in 2010: This project constructed eight aerated static pile concrete bins for
processing compost with a computer-controlled aeration process. Exhaust
air is filtered through a new biofilter to scrub out moisture and odor.
Aldermanic Wards: All Wards
BACK TO THE TOP
SPENCER CREEK WASTEWATER TREATMENT PLANT EXPANSION - COMPLETED
Project Cost: $9,200,000
Contractor: KCI Construction
Completed in 2010: This project increased the treatment capacity at the 20-year-old Wastewater Treatment Plant by 40% to 9.5 million gallons per day. The project upgraded the oxidation basin equipment (in the part of the plant where bacteria feed on organic material), added a new final clarifier tank (where biosolids and lighter materials such as oil and grease are separated from water), added an ultraviolet light disinfection system, and installed a new plant power system with a backup power generator and new computerized supervisory controls.
Aldermanic Wards: All Wards
BACK TO THE TOP
SPENCER CREEK WASTEWATER TREATMENT PLANT SOLIDS DEWATERING FACILITY - COMPLETED
Project Cost: $4,004,000
Contractor: KCI Construction
Completed in 2009: This project upgrades the solids handling facilities at the
Wastewater Plant. Construction included a new aerated sludge holding
process, a new building with two 2-meter sludge dewatering processes and
a conveyor system to transport dewatered biosolids to a holding bunker.
The dewatered biosolids are combined with ground yard waste in a
feedstock mixer and processed into compost at the City’s Earth Centre
organic recycling facility.
Aldermanic Ward: All Wards
BACK TO THE TOP